TEMCO Bell Bay Tasmania

Capacitor Bank Switching Studies

Carried out transient switching studies for back to back switching of power factor correction capacitor banks

May 2005

BlueScope Steel Springhill works

Feasibility studies for power factor correction and harmonic filtering

Prepared feasibility studies for power factor correction and harmonic filtering associated with upgrade of Coupled Pickle Cold Mill main drive power conversion equipment

May 2005

BHP Billiton Mitsubishi Alliance

Due Diligence study for Refurbishing of second hand dragline

Assisted BMA personnel to carry out due diligence investigation of the capability of Flanders Electric to refurbish the electrics for a secondhand dragline

June 2005

Glennies Creek Coal

Transient over voltage studies for Glennies Creek Colliery

Carried out transient studies to investigate cause of failure of underground transformers

June 2005

TEMCO Bell Bay Tasmania

22 kV Switchboard Fault Investigation

Investigated the coupling of 22 kV earth faults into low voltage equipment

September 2005

Thiess

Project Magnet 33 kV Earth fault calculations

Prepared calculations of earth fault currents for 33 kV transmission line between South Middleback and Middleback

September 2005

BlueScope Steel Port Kembla Steelworks

21 Area Power Distribution

Prepare a feasibility study for the upgrade of the power distribution in 21 Area

August 2005

BlueScope Steel Springhill works

CPCM Harmonic Filter Design

Prepared design calculations for power factor correction and harmonic filtering associated with upgrade of power conversion equipment for Coupled Pickle Cold Mill main drives

August 2005

BlueScope Steel Western Port

Coiler Switchroom Fire Investigation

Prepared a report on the possible cause of switchroom fire at BlueScope Steel Western Port site

September 2005

OneSteel Sydney Steel Mill

Harmonic Filter Tuning Coil failure Investigation

Prepare transient switching and load studies to determine whether these had any influence in failure of tuning coils

September 2005

New Zealand Steel Glenbrook NZ

3.3 kV Switchgear failure Investigation

Investigated the cause of the failure of a 3.3 kV vacuum contactor starter for 1.8 MW motor

November 2005

Inspect Consulting

Protection setting Report for Boral Deer Park Waste to Energy Project

Prepared protection setting report for gas engine embedded generator

November 2005

OneSteel Whyalla

Iron Knob Load flow and fault studies for new load

Prepared load flow and fault studies to assess the effects of additional new load on supply to existing consumers

December 2005

BlueScope Steel

CPCM drive convertor staging

Investigation of the staging of upgrading of the CPCM main drives and the use of MG set synchronous motors as synchronous condensers

January 2006

RailCorp

Blacktown Substation transformer Design Brief

Prepared a design brief for specification of 66/33 kV transformer for Blacktown substation

February 2006

BlueScope Steel Springhill works

MG Set 6.6 kV circuit Breaker Failure Investigation

Investigated and reported on possible causes of failure of Reyrolle C class bulk oil circuit breaker

February 2006

BlueScope Steel Port Kembla Steelworks

Steelworks Co-generation Project

Loadflow and fault studies to determine impact of co-generation project

February 2006

BHP Billiton Mitsubishi Alliance

Assessment of Dragline Load on TSS

Analysed recorded load data for two draglines for estimating loading on transportable substation

February 2006

TPA Consultants

Voltage Drop Calculations

Prepared voltage drop calculations for DOL and auto-transformer starting of fan motor

March 2006

TEMCO Bell Bay Tasmania

Power System Capacity Review

Reviewed the capacity of power distribution system for TEMCO Bell Bay site including assessment of loads from SCADA data, loadflow, fault studies and harmonic studies

March 2006

Simmons Project Services Devonport Tasmania

Investigation of unbalanced current sharing on low voltage mains cables

Prepared calculations of cable admittances and estimated level of unbalance. Prepared recommendations to correct unbalance

May 2006

TEMCO Bell Bay Tasmania

Capacitor bank upgrade

Prepared loadflow, fault, harmonic and transient switching studies for upgrade of capacitor banks for F1, F2 and F5 furnaces

May 2006

OneSteel Whyalla

Ladle Furnace Overcurrent trips

Assisted OneSteel personnel to investigate causes of overcurrent trips on ladle furnace

June 2006

BlueScope Steel Western Port

Peer Review for Substation upgrade

Participated in peer review of feasibility study for the upgrade of SY33 substation

July 2006

OneSteel Whyalla

Coke Ovens No 1 Substation Upgrade Feasibility Study

Feasibility study including load assessment load flow and fault studies for the upgrade of CO No1 substation

September 2006

BlueScope Steel Erskine Park Service Centre

Protection Setting Studies

Prepared report on recommended protection settings including fault studies and protection coordination studies

September 2006

Simmons Project Services

Protection Setting Studies for Caterpillar Underground

Prepared fault studies and protection coordination studies and recommended protection settings for the upgrade of the supply substation for Caterpillars works

August 2006